News

155 billion Naira Abuja-Kano road contract over priced-Reps

By Gift Chapi Odekia

Members of the House of Representatives have disclosed that the contract for the construction of the Abuja-Kaduna-Kano dual carriage way awarded to Julius Berger Nigeria at the cost of N155 billion with a completion period or 36 weeks was over priced.

Members of the House committee on works made the disclosure during an oversight visit to the road site.

According to the committee, at the time the contract was awarded to Julius Berger, there were other companies who quoted about N90 billion for the 375 kilometer road, insisting that even though there is no commensurate work done compare to the money paid so far, it must be delivered on schedule.

The Chairman of the Committee Rep. Abubakar Kabir told newsmen that while Julius Berger has collected about N70 billion from the Federal government, an accessment of the work done so far revealed that the contractor were yet to accomplish more than 20 percent of the total work.

While the Lawmakers said the unit cost of the project per kilometer stands at about N450 million, the Zonal Director of Works for North West, Engr. Esan Folurunsho and the Engineer Representatives supervising the project, Engr. James Zira said the materials being used for the Kaduna to Zaria section of the road was cheaper for Nigeria.

The lawmakers had asked the Ministry officials the unit cost per Kilometer when Engr. Zira told them that the contractor was removing the old asphalt and resuming them for the road, adding that it was cheaper for the country.

“we are removing and reusing the asphalt on the road. It is a different method and cheaper concept. If we throw the asphalt away, it will have negative impact on the environment,” he said.

But Zira and his Director could not provide answer to questions of cost per unit for the Job, insisting that they must be allowed to return to the office to do a calculation of the unit cost, an answer which angered members of the Committee.

Deputy Chairman of the Committee, Rep Edu expressed displeasure over their inability to tell the committee the unit cost.

“You knew we were coming for this oversight. You should have prepared all these answers for us. This is unacceptable. You are telling us that what is being done here is cheaper for Nigeria and yet, you cannot tell us the unit cost.

Speaking to the ministry representatives the committee Chairman also expressed anger saying “you are not talking to novice. You are talking to Professionals. The unit cost per kilometer for this project is about N450 million. We are not dumb. The cost is too high. Julius Berger says they signed for rehabilitation and now they are are doing reconstruction. But even at that, the cost is far above the cost of a virgin road anywhere in the world.

“We have to protect the interest of Nigerians because this is our country. We dont have any other country to call our own. We don’t want anybody to send a memo to the President later regarding to funding for this project.

“What we are saying is that the cost for this project is too high. We know of some companies that quoted N90 billion for this project, but we don’t want to mention names. We have several petitions regarding this project in the House. The cost was initially N159 billion before it was scaled down to N155 billion.

“There is nine months left on the contract and we must emphasise that it must be delivered on schedule. There will be no extension. Otherwise, we wi apply the force of the constitution. We have a similar experience on the Lagos-Ibadan road and that project is almost 15 years now and it has not been completed. We don’t want that to repeat itself on this road.

“Julius Berger has confirmed to us that they don’t have funding problem. But the Julius Berger we knew in the past is not the same Julius Berger we have now. Their performance is far below expectations”.

He directed officials of the Federal Ministry of Works to ensure that an emergency measure is put in place to address issues of port holes causing accidents ok n a daily basis along the road.

The Zonal Director in charge of North West for the Ministry of Works said the road under construction was the first of it’s kind in the north, only comparable to the Lagos-Ibadan road and is designed to last for 30 years.

Representatives of Julius Berger, Mark Jefferson assured the committee that the work will be delivered on schedule, be it was quick to add that the only problem that may delay the project will be the issue of compensation and relocation which is being handled by the Ministry.

He disclosed that section two of the project running from Kaduna to Zaria is presently 62 percent completed, while sections of the road that are 100 percent completed have been opened to traffic.

Related Posts

Leave a Comment

This News Site uses cookies to improve reading experience. We assume this is OK but if not, please do opt-out. Accept Read More